Carson's Corner · Entrepreneurship & Investing

The Definitive 2026 Data Center Development & Investment Guide

Data centers have become the fastest-growing real estate asset class on earth — and the rules are nothing like traditional development. This is the complete, plain-English playbook for developers, investors, landowners, utilities, and municipalities: why power, not land, is now the binding constraint; how megawatts, substations, and interconnection queues actually work; why retired coal plants, steel mills, and brownfields are turning into gold mines; how sites are selected, underwritten, and priced; the AI buildout driving demand; the best US markets; why the TVA region and Tennessee are emerging hot spots; future trends through 2035; and a 150+ question FAQ with land, brownfield, and utility due-diligence checklists.

HyperscaleColocationEdgeAI TrainingAI InferencePowered LandMegawattsInterconnectionSubstationsBehind-the-MeterBrownfieldsCoal Plant ConversionOpportunity ZonesWater & CoolingDark FiberSite SelectionUnderwritingCost per MWAI FactoriesTVATennesseeSMRsNatural Gas150+ FAQ
Data center building lit gold at dusk beside high-voltage transmission towers, with a glowing outline of Tennessee and an AI chip icon overhead — illustrating the power-driven data center buildout in the TVA region.

Executive Summary

In the span of about three years, data centers went from a quiet, specialized corner of commercial real estate to the single most sought-after asset class in the country. The reason is simple: artificial intelligence turned computing into an industrial activity, and industrial activity needs an enormous, physical home — land, steel, water, fiber, and above all electricity. The companies racing to build that home are some of the most creditworthy tenants in the world, and they are signing leases measured not in square feet but in megawatts.

Why data centers became the fastest-growing real estate asset class

Traditional real estate is valued on location, rent, and cap rates. Data center real estate broke that model. A hyperscale operator does not care whether a parcel has a pretty view or sits on a popular retail corridor. It cares whether the site can deliver tens or hundreds of megawatts of reliable power, on a defined timeline, with fiber connectivity and water for cooling. When those boxes are checked, the land commands prices that would be unthinkable for the same dirt sold as industrial, agricultural, or residential ground. A 500-acre former coal plant that might trade as scrap-and-salvage industrial land can, with the right power infrastructure, be worth many multiples more as a data center campus. That repricing — driven by power, not place — is what makes the asset class explosive.

AI's impact on power demand

The defining shift is electrical. A conventional cloud or enterprise data center hall might run a rack at 5–10 kW. A rack packed with AI accelerators for training large language models can draw 40–130 kW or more, and next-generation systems push higher still. Multiply that across thousands of racks and a single AI campus can demand 100 MW to over 1 GW — the power footprint of a mid-sized city. For the first time in decades, electricity demand growth in the United States is being driven materially by a single new category of customer. Utilities that spent twenty years planning around flat load are now fielding interconnection requests that dwarf anything in their history.

Why power matters more than land

This is the sentence that reorganizes everything: "The first question isn't how many acres. It's how many megawatts." Land is abundant and relatively cheap. Deliverable, reliable, near-term power is scarce, expensive, and slow. You can entitle and grade a site in months; bringing a new high-voltage interconnection and substation online can take years and tens of millions of dollars. The result is that the value, the risk, and the competitive moat in data center development all migrate toward power. Whoever controls — or can credibly deliver — megawatts controls the deal.

Why brownfields are becoming strategic assets

Because power is the bottleneck, the most valuable parcels are often the ones that already sit on top of heavy electrical infrastructure. That describes the old industrial economy almost perfectly: retired coal-fired power plants, shuttered steel mills, idle paper mills, and large manufacturing complexes. They come with existing substations, high-voltage transmission, industrial zoning, water rights, rail, and large contiguous acreage. A retired coal plant may have a 230 kV or 500 kV switchyard and an interconnection that a greenfield developer would wait half a decade to obtain. The infrastructure of the 20th-century industrial economy is becoming the foundation of the 21st-century AI economy.

The opportunity — for every player at the table

Developers

Control powered or power-adjacent land, secure interconnection, and deliver shovel-ready or powered-shell sites to hyperscale and colocation tenants at a substantial development spread.

Investors

Underwrite long-duration, investment-grade-backed cash flows — or take development-stage land basis positions in the path of power and demand.

Utilities

Capture decades of new load growth, justify transmission upgrades, and structure large-load tariffs, behind-the-meter, and generation partnerships.

Municipalities

Convert tax-dormant brownfields into the largest property-tax and capital-investment base in the county — often with minimal demand on schools or traffic.

Landowners

Discover that acreage near transmission, substations, or fiber routes may be worth far more for compute than for any prior use — if it can be powered.

The chapters that follow unpack each of these in depth, starting with the basics — what a data center actually is — and building toward the megawatt math, the brownfield thesis, the underwriting framework, and a 150+ question reference FAQ.

Work With Carson

Have a Question? Talk to Carson

Whether you're buying, selling, or evaluating a commercial real estate deal, Carson Jones and Passive Investments can help. Text to start a conversation, or explore his brokerage services.

Chapter 1 — What Is a Data Center?

A data center is a purpose-built facility that houses computing hardware — servers, storage, and networking — together with the power, cooling, and connectivity needed to keep that hardware running continuously. At its simplest, it is a building optimized to convert electricity into computation and to remove the resulting heat. Everything distinctive about data center real estate flows from those two jobs: feeding power in, and getting heat out.

Physically, a data center is organized around the white space (the raised-floor or slab area where IT racks live) and the gray space (the supporting mechanical and electrical plant — switchgear, uninterruptible power supplies, generators, chillers, and cooling distribution). A facility is described less by its square footage than by its critical IT load in megawatts — the amount of power available to the computing equipment itself, separate from cooling and overhead.

Types of Data Centers

Not all data centers are the same animal. The category drives the tenant, the lease structure, the power density, and the kind of land and power a developer needs to assemble.

TypeWho operates itTypical sizeWhat it's for
HyperscaleCloud & AI giants (AWS, Microsoft, Google, Meta, Oracle)30 MW – 1 GW+ campusesMassive cloud platforms and AI training/inference at enormous scale
ColocationOperators like Equinix, Digital Realty, QTS, CyrusOne5 MW – several hundred MWLeasing space/power to many tenants (retail colo) or single large tenants (wholesale colo)
EnterpriseA single company for its own use<1 MW – tens of MWA corporation's own IT — banks, hospitals, manufacturers
EdgeCarriers, content & cloud providerskW – a few MWSmall, distributed sites close to users to cut latency
AI TrainingAI labs & hyperscalers50 MW – 1 GW+Dense GPU clusters training large models; extreme power density
AI InferenceCloud & AI providers1 MW – hundreds of MWServing trained models to users; often closer to population centers

Hyperscale

Hyperscale facilities are the giants — campuses built by or for the largest cloud and AI operators. They are designed for standardization, rapid replication, and immense scale, often planned in phases that grow from tens of megawatts to several hundred or more. Hyperscale tenants are the most powerful force in the land market because their power appetite is effectively unbounded and their credit is exceptional.

Colocation

A colocation ("colo") provider builds the shell, power, and cooling, then leases capacity to others. Retail colocation serves many smaller tenants who rent racks or cages; wholesale colocation leases large, dedicated blocks of power (often whole data halls) to single large customers — frequently the hyperscalers themselves, who lease wholesale capacity to supplement what they build.

Enterprise

An enterprise data center is owned and run by one organization for its own workloads. Once the default model, enterprise has steadily migrated to cloud and colo, but banks, hospitals, government, and certain manufacturers still run their own for control, latency, or compliance reasons.

Edge

Edge data centers are small facilities placed close to end users — in or near metro areas, at the base of cell towers, or inside existing buildings — to reduce latency for applications like streaming, gaming, autonomous systems, and real-time AI inference. They trade scale for proximity.

AI Training Facilities

AI training facilities exist to train large models. They concentrate thousands of GPUs into tightly networked clusters, producing the highest power densities in the industry and enormous cooling demands. Because training is somewhat latency-tolerant, these facilities can be sited wherever large blocks of cheap, reliable power exist — which is exactly why power-rich regions and brownfields matter.

AI Inference Facilities

Inference facilities run already-trained models to answer user requests. Inference is more latency-sensitive than training, so these tend to sit closer to population centers and often blend into colocation and edge footprints. As AI usage scales, inference is expected to become the larger long-run share of compute.

The major entities you'll encounter

Amazon Web Services (AWS)

The largest cloud provider; one of the most aggressive builders of hyperscale capacity and a relentless consumer of power and powered land.

Microsoft

Azure cloud plus deep AI ties; a leading driver of new campus development and large power-purchase and nuclear deals.

Google

Google Cloud and AI workloads; long-time hyperscale developer with major investments in clean power and advanced cooling.

Meta Platforms

Builds enormous owned campuses for AI and social workloads; known for very large single-site power commitments.

Oracle

Oracle Cloud Infrastructure has become a major AI-training host, signing some of the largest capacity deals in the market.

Behind these names sit the colocation developers (Equinix, Digital Realty, QTS, CyrusOne, Vantage, Switch and others) who build much of the physical capacity, plus the chipmakers — above all NVIDIA — whose hardware sets the power density that every building must be engineered around.

Chapter 2 — Why Data Centers Are Exploding

Data center demand has compounded for two decades on the back of the internet, mobile, and cloud computing. What changed recently is the arrival of a second growth engine — artificial intelligence — layered on top of an already-growing base. The combination has produced demand that is straining the power grid itself.

AI Demand

AI is the accelerant. Training and running large models is extraordinarily compute-intensive, and that compute translates directly into power and physical space.

ChatGPT and the consumer AI moment

The public launch of ChatGPT turned AI from a research curiosity into a mass-market product overnight, triggering a global race to build the infrastructure behind it. Every major technology company responded by committing tens of billions of dollars to compute capacity, and that capital lands as concrete, steel, and megawatts.

LLMs (large language models)

Large language models are trained on vast datasets using enormous clusters of accelerators running for weeks or months. Each new generation of model tends to demand more compute than the last, and training is only half the story — once trained, models must be served continuously.

GPU clusters

Modern AI runs on GPU clusters (and related accelerators) wired together with high-speed networking so thousands of chips behave like one machine. These clusters are the densest, hottest, most power-hungry hardware ever deployed at scale, and they are the reason rack densities jumped from single-digit kilowatts to many tens of kilowatts.

Inferencing

Inferencing — actually using a trained model to generate answers — is where AI meets the user. As adoption grows, aggregate inference demand can exceed training demand, and because it is latency-sensitive, it pulls capacity toward population centers and the edge.

Cloud Computing

Underneath the AI wave, ordinary cloud computing keeps growing. Businesses continue migrating workloads off their own servers and into AWS, Azure, Google Cloud, and Oracle. Every SaaS app, streaming service, and corporate system that moves to the cloud adds steady baseline demand for data center capacity independent of AI.

Digital Transformation

Across every industry, "digital transformation" — moving operations, records, and customer interactions online — generates data and the need to store, process, and protect it. The long migration from paper and on-premises systems to digital and cloud is nowhere near finished and adds durable, recurring demand.

Autonomous Vehicles

Self-driving systems generate and consume staggering amounts of data — training perception models, processing sensor feeds, running simulations, and updating fleets. As autonomy advances, both the training (centralized) and the real-time inference (edge) components push data center demand higher.

Robotics

Industrial and consumer robotics, increasingly powered by AI, depend on models trained in data centers and, often, on low-latency inference nearby. The same compute backbone behind language models underlies the coming wave of physical automation.

Defense Applications

National defense and intelligence increasingly rely on AI, simulation, and large-scale data processing — much of it in secure, often domestically sited facilities. The strategic importance of compute has made data centers a matter of national security as well as commerce.

Healthcare

Genomics, medical imaging, drug discovery, and AI-assisted diagnostics are all compute-heavy. Healthcare's digitization and its adoption of AI add another durable demand stream, often with strict data-residency and security requirements that favor specific facilities and locations.

The takeaway: AI is the headline, but it sits on top of cloud, digital transformation, autonomy, robotics, defense, and healthcare — several independent growth curves stacking at once. That is why the demand is not a spike but a structural step-change, and why it is colliding with the physical limits of the power grid.

Chapter 3 — The New Currency Is Power

If you remember one chapter, make it this one. The entire data center land market reorganizes around a single resource: electricity. Power is the currency. Everything else — acreage, zoning, fiber, even water — is negotiable or solvable. Power is the constraint that makes or breaks a site.

Why Land Doesn't Matter Without Power

A perfect 1,000-acre parcel — flat, dry, well-zoned, fiber overhead — is worth very little to a data center developer if it cannot get power for seven years. Conversely, a modest 80-acre site adjacent to a large substation with available capacity can be worth a fortune. This inverts the traditional real estate hierarchy, where location leads. In data centers, the binding question is delivery of megawatts, and that is why the industry repeats the same line:

"The first question isn't how many acres. It's how many megawatts."

Land is a commodity input; reliable near-term power is the scarce asset. A developer's real job is often less about real estate and more about securing an electrical interconnection — navigating the utility, the queue, the substation, and the transmission system. Whoever solves power wins.

Understanding Power Capacity

Data center scale is measured in megawatts (MW) and, increasingly, gigawatts (GW). Here is a rough sense of what different capacities mean.

CapacityRough scaleWhat it represents
10 MWSmall / single buildingA modest colocation facility or one data hall; powers on the order of several thousand average US homes.
50 MWMid-size facilityA solid single-building or small-campus deployment; a meaningful new load for many utilities.
100 MWLarge facility / small campusA major hyperscale building or phase; tens of thousands of homes' worth of power.
500 MWMajor campusA large multi-building AI/cloud campus; requires dedicated transmission and substation infrastructure.
1 GW (1,000 MW)Mega-campusCity-scale load. The frontier of AI campuses; often needs new generation, not just new wires.
10 MW

Single building / small colo

100 MW

Hyperscale building or phase

1 GW

City-scale AI mega-campus

Utility Constraints

The utility is the gatekeeper. Whether — and when — a site can be powered depends on the local utility's available capacity, its transmission system, its interconnection process, and its willingness and ability to build new infrastructure. A site in a constrained service territory may face multi-year waits or be told that large new load simply cannot be served near-term. Understanding the serving utility is step one of any site evaluation.

Substations

A substation steps high-voltage transmission power down to levels a data center can use, and is the physical point where a campus connects to the grid. Proximity to a substation with available capacity — or the ability to build a new one and tie into nearby transmission — is one of the most valuable attributes a site can have. Substation buildouts are expensive and slow, so existing capacity is gold.

Transmission Lines

High-voltage transmission lines (often 115 kV, 138 kV, 230 kV, 345 kV, or 500 kV) are the highways that move bulk power. A site near high-capacity transmission has a far shorter, cheaper path to large-scale power than one that would require miles of new line. The voltage and spare capacity of nearby lines materially affect how much load a site can ultimately support.

Interconnection Queues

To connect large new load (or new generation) to the grid, a project must enter the utility's or grid operator's interconnection queue and undergo studies that determine what upgrades are needed and who pays for them. These queues have become badly congested, and timelines of several years are common. A site's effective value is heavily influenced by its position in — or ability to bypass — the queue.

Behind-the-Meter Generation

Because the grid is slow, many developers are turning to behind-the-meter generation — building power on-site rather than waiting for the utility. This can dramatically compress timelines and is one of the defining trends of the current cycle.

Natural Gas

On-site natural gas generation (turbines or reciprocating engines) can bring large blocks of power online relatively quickly where gas pipelines exist. It is a leading bridge solution for AI campuses that cannot wait for grid interconnection, though it carries emissions and permitting considerations.

Nuclear

Nuclear power — including restarting retired reactors, co-locating at existing nuclear plants, and future small modular reactors (SMRs) — has become a serious strategy for delivering large, firm, carbon-free power to data centers. Several major operators have signed nuclear-related deals, signaling that the largest players will pay for firm power and are willing to underwrite new generation.

The big power players you'll encounter

Duke Energy

A major utility across the Carolinas and Southeast; a key gatekeeper for data center load in fast-growing southern markets.

Tennessee Valley Authority (TVA)

The federal utility serving Tennessee and parts of six neighboring states; large generation base, competitive rates, and central geography make its territory a rising data center magnet.

Dominion Energy

Serves Virginia, home to "Data Center Alley" (Ashburn) — the densest data center market on earth and a case study in both demand and grid strain.

Chapter 4 — How Developers Evaluate Data Center Land

Once power is established as the lead criterion, developers run every prospective site through a multi-factor screen. A parcel that passes the power test still has to clear a long list of physical, regulatory, and economic checks. Here is the working framework, factor by factor.

Site Selection

Site selection is a process of elimination. Developers and their engineers score candidate parcels against a weighted set of criteria, weeding out anything with a fatal flaw — no near-term power, in a floodway, unbuildable topography, hostile zoning — before spending real money on diligence. The factors below are the core of that screen.

Acreage

Data center campuses need room — for the buildings themselves, for generators and cooling plant, for substations and switchyards, for security setbacks, and for future phases. A single large building might sit comfortably on 20–50 acres, while a multi-phase hyperscale campus can absorb 200–1,000+ acres. Contiguity matters: large, unbroken tracts are far more valuable than the same acreage split by roads, easements, or parcels.

Topography

Flat, gently graded land is ideal. Steep slopes, rock, and irregular terrain raise earthwork and foundation costs and can sterilize portions of a site. Developers favor parcels that minimize cut-and-fill and allow efficient building pads and equipment yards.

Flood Zones

Data centers are mission-critical and cannot tolerate flooding. Sites in FEMA floodways or high-risk flood zones are heavily disfavored; even partial flood exposure complicates insurance, financing, and tenant approval. Clean, well-drained ground above flood risk is a baseline requirement.

Environmental Issues

Contamination, wetlands, endangered-species habitat, and historical/archaeological constraints can all delay or block development. On brownfields this cuts both ways — the same industrial history that delivers power infrastructure can also bring remediation obligations. Phase I and, where warranted, Phase II environmental assessments are standard.

Fiber Access

A data center is useless without connectivity. Proximity to long-haul fiber routes and multiple carriers reduces the cost and risk of bringing in the bandwidth a facility needs. Sites along established fiber corridors — often following highways, rail, or pipeline rights-of-way — have a real advantage.

Water Availability

Many cooling designs consume significant water. Access to municipal water, wells, or surface water — and the legal right to use it — can be decisive, especially for large campuses in dry regions. Even air-cooled or closed-loop designs benefit from water access as a backstop. Water is covered in depth in Chapter 7.

Utility Access

Beyond electricity, sites need the full utility picture: gas (increasingly, for on-site generation), water and sewer, and telecom. The presence, capacity, and cost of extending these services factor into both feasibility and budget.

Labor Availability

Construction requires a large skilled workforce — electricians, mechanical trades, and specialized contractors — and operations require technicians. While data centers employ relatively few people once running, the construction phase is labor-intensive, and regions with deep trade labor pools build faster and cheaper.

Tax Incentives

States and localities compete hard for data centers with sales-tax exemptions on equipment, property-tax abatements, and other incentives. These can swing project economics meaningfully, and the strength of a jurisdiction's incentive program is a genuine site-selection factor. Incentives also signal a community's willingness to host the use.

Zoning

The right zoning — typically industrial or a purpose-built data center designation — and a cooperative local government dramatically de-risk a project. Sites that are already appropriately zoned, or in jurisdictions with clear approval pathways, are worth more than those requiring rezoning, variances, or contentious public hearings. Entitlement certainty has real value.

How it fits together: think of site selection as a funnel. Power capacity and timeline sit at the top and eliminate most parcels immediately. Survivors are then ranked on acreage, topography, flood risk, environmental condition, fiber, water, utilities, labor, incentives, and zoning. The rare site that scores well on all of them — especially a brownfield that arrives with power and zoning already in place — is what the entire market is hunting for.

Chapter 5 — Brownfields Become Gold Mines

This is the most counterintuitive — and most lucrative — idea in the entire guide. The retired, rusting industrial sites that communities often write off as liabilities are frequently the single best data center sites in their region. Why? Because they already sit on top of the one thing everyone else is fighting for: power.

What Is a Brownfield?

A brownfield is a previously developed industrial or commercial site that is idle, underused, or abandoned, often with some real or perceived environmental contamination. Classic examples include retired power plants, closed factories, old steel and paper mills, rail yards, and chemical or manufacturing complexes. They contrast with greenfields — undeveloped land with no prior industrial use.

Why Data Centers Love Brownfields

For most uses, a brownfield's industrial baggage is a drawback. For data centers, the very features that made a site industrial are exactly what a hyperscale campus needs. The match is almost uncanny.

Existing Power Infrastructure

Heavy industry consumed enormous power, so these sites often have large existing electrical service, on-site substations, and transmission ties — the scarcest, slowest, most expensive thing to build new.

Industrial Zoning

Already zoned for intensive industrial use, sidestepping the rezoning fights and public opposition that greenfield projects often face.

Utility Connections

Existing water, sewer, gas, and telecom service — and a utility already accustomed to serving large load at the location.

Large Tracts

Industrial sites tend to be big and contiguous — hundreds of acres in single ownership, ideal for multi-phase campuses.

Existing Substations

A working switchyard and substation can save years and tens of millions versus building from scratch, and may sidestep parts of the interconnection queue.

Coal Plant Redevelopment

Retired coal plants are the crown jewels — high-voltage interconnection, large land, water rights, rail, and a community motivated to replace lost jobs and tax base.

Coal Plant Redevelopment

Retired coal-fired power plants deserve their own spotlight. When a coal plant shuts down, its generation goes away — but its grid interconnection does not. The high-voltage switchyard, the transmission ties, the cooling-water access, and often rail and large acreage remain. That interconnection was sized to export hundreds of megawatts to the grid; a data center can run that flow in reverse, importing large load through infrastructure that already exists. This is why coal-plant sites have become some of the most fought-over parcels in the country.

The old industrial economy becomes the infrastructure for AI

There is a poetic symmetry here. The mills and plants that powered the 20th-century industrial economy are being reborn as the foundation of the 21st-century AI economy. The transmission lines built to move power from a coal plant now move power to a compute campus. The rail spur that brought in coal can bring in transformers and gear. The water that cooled turbines now cools servers. Examples of brownfields finding new life as data centers include:

Case Study Framework — Former Coal Plant

Consider a hypothetical that mirrors deals happening across the country. (Illustrative figures, not a specific transaction.)

AttributeThe siteWhy it matters for data centers
Land500 acresRoom for a large multi-phase campus plus substation, generation, and setbacks.
Transmission230 kV tiesExisting high-voltage interconnection — years and tens of millions saved.
SubstationExisting switchyardA physical grid connection point already built and energized.
RailActive spurMove heavy transformers, switchgear, and equipment cost-effectively.
WaterPermitted intakeCooling water rights already established — a major entitlement.

Why this may be worth more as a data center than as industrial land

Sold as generic industrial land, a 500-acre former coal plant might trade at industrial-acre pricing, discounted for demolition and remediation. But to a hyperscale developer, the interconnection and substation alone can be worth more than the land — because the alternative is a five-to-seven-year wait and a nine-figure infrastructure spend on a greenfield. When power is the binding constraint, a site that delivers power on day one commands a premium that has nothing to do with traditional land comps. That gap — between industrial-land value and powered-data-center value — is the brownfield opportunity in one sentence.

The catch: brownfields carry real diligence risk — environmental remediation, demolition cost, the actual usable capacity of "existing" infrastructure (which may be aged or undersized), and clear title to interconnection rights. The thesis is powerful, but each of these must be verified, not assumed. A brownfield is a gold mine only after the assays come back clean.

How to Determine the Highest & Best Use of an Obsolete Industrial Site

When a factory, mill, or plant goes dark, the owner faces a deceptively simple question: what is this property actually worth now? The answer depends on its highest and best use — the legally permissible, physically possible, financially feasible, and maximally productive use of the site. For a growing number of obsolete industrial properties, that use is no longer manufacturing, warehousing, or scrap-and-salvage land. It may be a data center, an industrial outdoor storage (IOS) yard, an enterprise IOS (EIOS) campus, or a logistics facility — and the gap between the old use and the best use is where value is unlocked.

The four tests of highest and best use

Appraisers and developers screen every candidate use against four filters. A use only qualifies as "highest and best" if it passes all four.

1. Legally permissible

What does the zoning, entitlement, and deed allow — and what could realistically be rezoned or variance-approved? Industrially zoned brownfields already clear this hurdle for data centers, IOS, and heavy logistics, which is a major head start.

2. Physically possible

Does the site's acreage, topography, soils, flood exposure, and existing infrastructure support the use? A 500-acre flat parcel with a substation supports a data center; a 15-acre paved yard near an interchange supports IOS.

3. Financially feasible

Does the use generate enough value to justify the cost of conversion, including demolition and remediation? Power infrastructure and paving that already exist tilt feasibility dramatically.

4. Maximally productive

Of the uses that pass the first three tests, which produces the greatest value? This is where a powered brownfield's data center value can eclipse its industrial value many times over.

Common highest-and-best-use outcomes for obsolete industrial sites

Site profileLikely highest & best useKey value driver
Large acreage near transmission / substationData center campusDeliverable power (megawatts)
Mid-size paved yard near highway interchangeIndustrial outdoor storage (IOS)Access, paving, truck circulation
Paved yard with buildings & office near port/railEnterprise IOS (EIOS)Fleet, equipment & operations base
Clear-span building near population centerWarehouse / last-mile logisticsProximity to demand
Powered brownfield inside an Opportunity ZoneData center + OZ structurePower plus tax treatment

The discipline is to test the site against each use rather than defaulting to its prior life. An obsolete factory is not "a factory that no longer works" — it is a bundle of power, acreage, access, and entitlements that some buyer values more than you might expect. Determining which buyer, and which use, is the whole game.

10 Signs Your Industrial Property Is Worth More Than Its Current Use

Many owners of aging industrial real estate are sitting on far more value than their current rent roll or tax assessment suggests — because the market is now pricing power, access, and acreage rather than the building. If your property shows several of the signs below, it may be worth ordering a fresh highest-and-best-use analysis before you renew a low lease, accept a scrap-land offer, or let it sit idle.

  1. It sits near high-voltage transmission or a substation. Proximity to deliverable power is the single most valuable attribute a site can have in the data center era. Lines at 115 kV and above, or an on-site or adjacent substation, are a major flag.
  2. It has large existing electrical service. Heavy manufacturing, mills, and plants drew enormous power. That existing service — and the interconnection behind it — can be worth more than the land itself.
  3. It's a retired power plant or heavy-industrial site. Retired coal plants, steel mills, and paper mills often retain switchyards, transmission ties, water rights, and rail — exactly what data center developers pay premiums for.
  4. It offers large, contiguous acreage. Unbroken tracts of 50, 200, or 500+ acres in single ownership are increasingly scarce and are prized for multi-phase campuses.
  5. It has water rights or a permitted intake. Cooling water — municipal, well, surface, or reclaimed — is a genuine entitlement that raises value for compute and heavy industrial reuse.
  6. It's on or near major fiber routes. Long-haul fiber and multiple carriers along nearby highway, rail, or pipeline corridors make a site far more attractive for connectivity-dependent uses.
  7. It has direct highway, interchange, or rail access. Strong access supports data centers (heavy equipment delivery) and is the core driver of industrial outdoor storage (IOS) and enterprise IOS (EIOS) value.
  8. It's already zoned industrial. Existing heavy-industrial or data-center zoning sidesteps the rezoning fights and public opposition that kill or delay greenfield projects — entitlement certainty has real, bankable value.
  9. It sits in an Opportunity Zone or an incentive-rich jurisdiction. Federal Opportunity Zone treatment plus state and local tax incentives can stack on top of the site's physical advantages.
  10. It's paved, fenced, and stabilized. A paved, secured yard with truck circulation is turn-key for IOS/EIOS demand — one of the fastest-growing industrial niches — without any vertical construction.

None of these signs is a guarantee, and each must be verified rather than assumed. But if your property checks three or more boxes, the odds are high that its highest and best use — and its market value — is materially above its current use. That gap is the opportunity.

How to Sell an Industrial Campus to Institutional Buyers

Selling a large industrial campus — a former plant, mill, or multi-building complex — to an institutional buyer (a hyperscaler, a data center developer, a REIT, or an infrastructure fund) is a fundamentally different exercise from selling to a local user. Institutional buyers underwrite risk, not charm. They pay premiums for certainty and discount heavily for ambiguity. The seller's job is to remove ambiguity before going to market.

1. Establish the highest and best use first

Before pricing or marketing, determine whether the campus is worth more as a data center site, an IOS/EIOS yard, logistics, or continued industrial use. The buyer universe, the value, and the entire sale strategy flow from that answer. Marketing a powered brownfield as generic industrial land can leave enormous value on the table.

2. Assemble the power and infrastructure story

For a data center buyer, power is the deal. Document the serving utility, available capacity, transmission voltages and proximity, substation condition, interconnection rights, and any behind-the-meter or gas options. A credible, evidenced power narrative is the difference between industrial-land pricing and powered-land pricing.

3. De-risk the diligence items up front

Institutional buyers will find every problem eventually; sellers who surface them early control the narrative. Commission a Phase I (and Phase II where warranted), an ALTA survey, title work, zoning confirmation, and environmental status before listing. Clean, organized diligence compresses timelines and defends price.

4. Confirm entitlements and community posture

Existing industrial zoning, a cooperative local government, and available incentives materially raise value and lower a buyer's execution risk. Where possible, secure or document the approval pathway so the buyer isn't pricing in a rezoning fight.

5. Build a professional data room

Package everything — surveys, environmental reports, utility correspondence, tax and incentive detail, title, and infrastructure records — into an organized data room. Institutional diligence teams move faster and bid higher when information is complete and credible.

6. Reach the right buyer universe

The buyers for a powered campus are a small, specialized group: hyperscalers' real estate teams, data center developers, infrastructure funds, and the brokers who serve them. Reaching them — rather than the local industrial market — is what produces competitive, institutional-grade offers.

7. Structure the deal to match buyer needs

Institutional buyers often prefer options, phased takedowns, or long due-diligence periods that let them confirm power before closing. Sellers who understand and accommodate these structures — while protecting themselves with deposits and milestones — attract more and better bids.

Do this with professionals: disposing of a large industrial campus to institutional buyers involves brokerage, legal, environmental, and utility expertise. Engage qualified advisors early; the value created by proper positioning typically far exceeds the cost.

Chapter 6 — Data Centers and Opportunity Zones

Few people connect these two topics, which is exactly why it is an opportunity. Opportunity Zones are designated economically distressed areas where investors can receive significant federal capital-gains tax benefits for long-term investment. Many of them happen to sit in exactly the kind of rural and post-industrial places where powered land and brownfields are found.

Opportunity Zone benefits

The Opportunity Zone program lets investors defer and potentially reduce tax on capital gains by rolling them into a Qualified Opportunity Fund that invests in property or businesses within a designated zone. The headline benefit is that appreciation on a qualifying investment held for the long term (generally ten years) can be excluded from federal capital-gains tax. The exact rules, dates, and percentages have evolved and must be confirmed with a tax advisor, but the structural incentive — favorable treatment for long-term investment in distressed areas — is the point.

Data center development in an Opportunity Zone

Data centers are capital-intensive, long-hold assets — precisely the profile the Opportunity Zone program rewards. A developer building a campus in a designated zone may pair an extraordinary operating asset (long-term, investment-grade-backed cash flow) with a powerful tax structure (deferral and potential exclusion of gains). When a brownfield with existing power also sits inside an Opportunity Zone, the stack of advantages — power, zoning, incentives, and tax treatment — can be remarkable.

Long-term capital gains

Because the largest Opportunity Zone benefit accrues to investments held for roughly a decade, the program aligns naturally with the long duration of data center leases and ownership. Investors sitting on large unrealized capital gains — from stock, a business sale, or other real estate — have a potential pathway to redeploy those gains into compute infrastructure on tax-advantaged terms.

Rural development

Many Opportunity Zones are rural, and so are many of the best power-rich data center sites — near generation, transmission, and water, away from congested metros. This overlap means data center investment can deliver on the program's original purpose (capital and jobs into distressed communities) while solving the industry's core problem (finding powerable land). It is one of the few topics where the tax policy, the community benefit, and the asset economics genuinely point the same direction.

Why this is underexplored: Opportunity Zone investors have historically focused on multifamily and conventional commercial real estate. Pairing the structure with powered land and data centers is far less common — which is exactly why it is worth understanding before it becomes consensus. As always, confirm current OZ rules and timelines with qualified tax counsel; the program's parameters change.

Chapter 7 — Water Requirements

After power, water is the resource that most often makes headlines and shapes community reaction. Data centers generate enormous heat, and removing that heat efficiently has historically involved water. How much water a facility uses depends entirely on its cooling design.

Air-Cooled Facilities

Air-cooled designs reject heat to the atmosphere using fans and chillers, consuming little or no water for cooling. They trade water for electricity — air cooling is generally less energy-efficient than water-based cooling, so a dry design lowers water use but can raise power use. In water-scarce regions, this trade is increasingly worth it.

Liquid Cooling

Liquid cooling brings coolant directly to the chips (via cold plates) rather than cooling the room air. It is far more effective at handling the extreme heat of AI hardware and is becoming standard for high-density GPU clusters. Depending on the system, it can use water more efficiently and enable much higher rack densities than air cooling allows.

Immersion Cooling

Immersion cooling submerges servers in a non-conductive fluid that carries heat away directly. It enables the highest densities and excellent efficiency, and closed-loop immersion can dramatically reduce water consumption. It is newer and adds operational complexity, but it is a leading direction for AI-era facilities.

Water Usage Concerns

Traditional evaporative cooling (cooling towers) can consume large volumes of water — a point of real public concern, especially in arid regions or during drought. Water Usage Effectiveness (WUE) has joined Power Usage Effectiveness (PUE) as a metric operators track and disclose. The industry is moving toward designs — air-cooled, closed-loop liquid, immersion, and reclaimed/non-potable water — that cut potable water draw.

Municipal Challenges

For a town or utility, a large data center's water demand can rival that of a sizeable population. This raises legitimate questions about capacity, drought resilience, and fairness to other users, and it has become a flashpoint in some communities. Developers increasingly address it head-on by using non-potable or reclaimed water, closed-loop systems, or dry cooling, and by being transparent about consumption. A site's water rights and the local utility's capacity are genuine site-selection factors — and a place where doing right by the community and doing right by the project align.

Cooling approachRelative water useRelative energy useBest fit
Evaporative / cooling towersHighLowerWater-rich regions, cost-sensitive cooling
Air-cooled (dry)Very lowHigherWater-scarce regions, drought risk
Liquid (direct-to-chip)Low–moderateEfficient at densityHigh-density AI/GPU halls
ImmersionVery low (closed loop)Very efficientExtreme density, water-sensitive sites

Chapter 8 — Fiber Is the New Railroad

In the 19th century, towns lived or died by the railroad. In the data center era, the equivalent is fiber-optic connectivity. Power lets a data center run; fiber lets it matter. A facility with abundant power but poor connectivity is a generator looking for a purpose.

Dark Fiber

Dark fiber is fiber-optic cable that has been laid but is not yet "lit" with active equipment — spare capacity in the ground. Access to dark fiber lets an operator light its own dedicated, high-capacity connections without waiting for a carrier to build new routes. Sites near abundant dark fiber can scale bandwidth quickly and cheaply.

Long-Haul Networks

Long-haul fiber networks carry traffic between cities and regions over long distances. Proximity to multiple long-haul routes gives a data center diverse, high-capacity paths to the rest of the internet. These routes often parallel highways, rail lines, and pipeline corridors — which is why sites along established infrastructure corridors tend to have good connectivity.

Carrier Hotels

A carrier hotel is a major interconnection facility where many networks meet and exchange traffic. Being on a route to one or more carrier hotels — or being near a major interconnection point — improves a site's connectivity options and reduces the cost of reaching many networks at once.

Redundancy

Mission-critical facilities need redundant, physically diverse fiber paths so that a single cut — a backhoe, a storm — cannot sever the site. Multiple carriers entering from different directions, along separate rights-of-way, is the gold standard. Connectivity redundancy sits alongside power redundancy as a core reliability requirement.

Latency

Latency — the delay for data to travel to and from the facility — is critical for some workloads and nearly irrelevant for others. AI training is largely latency-tolerant, so training campuses can sit far from population centers in power-rich areas. Inference, real-time applications, financial trading, and interactive services are latency-sensitive and pull capacity closer to users. Matching a site's connectivity and location profile to the intended workload is part of good underwriting.

The pattern: power and fiber both follow corridors — highways, rail, rivers, and pipelines — because that is where rights-of-way already exist. The best data center sites tend to sit where a power corridor and a fiber corridor cross. Brownfields, once again, often sit precisely at those crossings, because heavy industry located there for the same reasons.
Work With Carson

Have a Question? Talk to Carson

Whether you're buying, selling, or evaluating a commercial real estate deal, Carson Jones and Passive Investments can help. Text to start a conversation, or explore his brokerage services.

Chapter 9 — Understanding Megawatts (Definitions)

Answer engines and search both reward clear, self-contained definitions. This chapter is a glossary of the power and reliability concepts that govern data centers, each written as a direct answer to a direct question.

What is a megawatt (MW)?
A megawatt is a unit of power equal to one million watts, or 1,000 kilowatts. Power measures the rate of energy use at a moment in time. In data centers, capacity is described in megawatts of critical IT load — the power available to the computing equipment. A 100 MW data center can draw up to 100 million watts continuously when fully loaded.
How many homes does a megawatt power?
As a rough rule of thumb, 1 MW of continuous power is often said to serve on the order of several hundred to about a thousand average US homes, depending on the region, season, and how the figure is calculated (peak vs. average). A common shorthand is roughly 750–1,000 homes per MW. So a 100 MW data center represents power comparable to tens of thousands of homes — which is why utilities treat large facilities as city-scale load.
How much power does a data center use?
It varies enormously by type and size. A small enterprise or edge site may use well under 1 MW; a mid-size colocation facility might use 10–50 MW; a hyperscale building or phase commonly runs 50–150 MW; and a large AI/cloud mega-campus can reach 500 MW to more than 1 GW. The defining 2020s trend is that AI workloads have pushed per-facility power far higher than the cloud-era norm.
What is a gigawatt (GW)?
A gigawatt equals 1,000 megawatts, or one billion watts. Gigawatt-scale has entered the data center vocabulary because the largest AI campuses are now being planned at that level. A 1 GW campus has a power footprint comparable to a major city or a large power plant, and at that scale developers often must arrange new generation, not merely new transmission.
What is a kilowatt (kW) and rack density?
A kilowatt is 1,000 watts. Inside a data center, power is often discussed per rack in kilowatts. Traditional racks ran 5–10 kW; AI racks packed with accelerators can draw 40–130 kW or more. "Rack density" refers to how much power (and heat) each rack represents — and rising density is what drives liquid and immersion cooling.
What is critical IT load?
Critical IT load is the portion of a facility's power that actually feeds the computing equipment, as distinct from power used by cooling, lighting, and other overhead. Data center capacity is typically quoted as critical IT load in megawatts, because that is the capacity available to tenants' servers.
What is PUE (Power Usage Effectiveness)?
PUE is the ratio of a facility's total power to the power delivered to IT equipment. A PUE of 1.5 means that for every watt to the servers, half a watt goes to cooling and overhead. A perfect PUE is 1.0. Modern efficient facilities target PUE well below 1.3; lower is better and directly affects operating cost.
What is WUE (Water Usage Effectiveness)?
WUE measures the water a facility consumes relative to its IT energy use, typically expressed in liters per kilowatt-hour. It is the water analog of PUE. Operators increasingly track and disclose WUE as water concerns rise, and air-cooled or closed-loop designs aim to drive it toward zero.
What is N+1 redundancy?
N+1 redundancy means a system has the components needed to carry the load (N) plus one extra (the +1) so that a single failure or maintenance event does not interrupt operations. For example, if four cooling units are needed, an N+1 design installs five. It is a common, cost-effective reliability standard.
What is 2N redundancy?
2N redundancy means fully duplicating the system — two complete, independent sets of infrastructure (N + N), so an entire side can fail and the facility keeps running on the other. It is more expensive than N+1 but offers higher fault tolerance, common in mission-critical and high-tier facilities. Variants like 2N+1 add even more margin.
What is a hyperscale data center?
A hyperscale data center is a very large facility built by or for major cloud and AI operators, designed for massive, standardized, rapidly scalable capacity. Hyperscale campuses commonly range from tens of megawatts into the hundreds or beyond, and are the dominant force in the powered-land market.
What is colocation?
Colocation is a model where a provider builds and operates the data center and leases space and power to customers, who place their own equipment inside. Retail colocation serves many tenants renting racks or cages; wholesale colocation leases large dedicated blocks of power to single large customers.
What is edge computing?
Edge computing places compute close to where data is generated and used — in or near metro areas, at cell sites, or in distributed micro-facilities — to reduce latency. Edge data centers are small relative to hyperscale but numerous, and they grow with latency-sensitive applications like real-time AI, streaming, and autonomous systems.
What is a powered shell?
A powered shell is a data center building constructed with the structure, power, and cooling infrastructure brought to the site, but with the interior fit-out (the IT-specific build) left for the tenant to complete. It lets a tenant move faster than ground-up construction while customizing the inside. Delivering a powered shell is a common developer product.
What is shovel-ready or shovel-ready powered land?
A shovel-ready site is one where entitlements, zoning, environmental clearance, and utility commitments are in place so construction can begin with minimal delay. "Powered land" adds the crucial element of secured electrical capacity. Shovel-ready powered land is the most valuable raw input in the industry because it removes the two slowest risks: entitlement and power.
What is an interconnection?
An interconnection is the physical and contractual connection between a facility (load or generation) and the electric grid. For a data center, securing interconnection means getting the utility or grid operator to agree to deliver the required power, which involves studies, upgrades, agreements, and often a place in a queue.
What is a substation?
A substation is electrical infrastructure that transforms voltage — typically stepping high-voltage transmission power down to distribution levels a facility can use — and serves as the connection point to the grid. An on-site or nearby substation with available capacity is one of the most valuable features a data center site can have.
What is a switchyard?
A switchyard is the high-voltage area, often at a power plant or large substation, where transmission lines connect and are switched and protected. Retired power plants often retain valuable switchyards and transmission ties, which is a key reason their sites are coveted for data centers.
What is behind-the-meter generation?
Behind-the-meter generation is power produced on-site, on the customer's side of the utility meter — for example on-site natural gas turbines, fuel cells, solar, or in the future small modular reactors. It lets a data center bring power online without waiting for grid interconnection, a major strategy in the current power-constrained environment.
What is an interconnection queue?
An interconnection queue is the line of projects waiting for the studies and approvals needed to connect new load or generation to the grid. Queues have become heavily backlogged, with multi-year waits common, making queue position — or the ability to avoid the queue via existing infrastructure or behind-the-meter power — a critical variable.
What is a tier rating (Tier I–IV)?
Tier ratings (often associated with the Uptime Institute) classify data center reliability from Tier I (basic, single path, no redundancy) to Tier IV (fault-tolerant, fully redundant, highest availability). Higher tiers mean more redundant power and cooling, higher cost, and greater uptime guarantees. Tenants choose a tier based on how critical their workloads are.

Chapter 10 — The Best Markets for Data Centers

Data center activity concentrates in markets that combine power availability, connectivity, land, incentives, and proximity to demand. Here are several of the most important US markets and what defines each.

Ashburn, Virginia

Ashburn and the surrounding Loudoun County corridor — "Data Center Alley" — is the largest and densest data center market in the world. Decades of fiber infrastructure, a deep ecosystem of operators, and proximity to a major internet interconnection point made it the default. Its challenge today is its own success: power and land have grown scarce and expensive, and grid strain has pushed new development outward — which is precisely what is opening up emerging markets.

Dallas, Texas

Dallas–Fort Worth offers a large, growing market with abundant land, an independent and flexible grid (ERCOT), business-friendly policy, and strong connectivity. Texas's energy resources and pro-development stance have made it a magnet for new capacity, including power-intensive AI projects.

Phoenix, Arizona

Phoenix has become a top-tier market thanks to large available land, relatively low natural-disaster risk, strong incentives, and aggressive utility support — balanced against water scarcity, which makes cooling design and water strategy especially important there.

Atlanta, Georgia

Atlanta has surged as a major Southeast hub, with competitive power, strong fiber, attractive incentives, and central regional geography. It exemplifies the shift of growth toward Southern markets with available power.

Nashville, Tennessee

Nashville anchors a fast-growing Tennessee market, benefiting from TVA power, central US geography, strong fiber routes, business-friendly policy, and a growing tech presence. It is part of the regional story explored in depth in Chapter 11.

Memphis, Tennessee

Memphis combines TVA power, abundant water from the Memphis Sand aquifer, a central logistics location, available industrial land, and major fiber and rail infrastructure. It has drawn significant attention — including very large AI projects — as a rising power-rich market.

MarketKey strengthWatch-out
Ashburn, VALargest ecosystem, fiber densityPower/land scarcity, grid strain, high cost
Dallas, TXLand, ERCOT grid, policyGrid weather events, competition
Phoenix, AZLand, low disaster risk, incentivesWater scarcity
Atlanta, GAPower, fiber, incentives, geographyRising competition for power
Nashville, TNTVA power, central geography, growthEmerging — infrastructure still scaling
Memphis, TNTVA power, water, logistics, fiberWater-use scrutiny, emerging market

The throughline: as established markets like Ashburn hit power and land limits, demand spills into power-rich, land-rich, incentive-friendly regions — and the Southeast and the TVA footprint are major beneficiaries.

Chapter 11 — Why Tennessee Is Becoming a Data Center Market

Tennessee sits at the convergence of nearly every factor that matters: large, competitively priced power; abundant water; central geography; strong fiber; and a business-friendly climate. For anyone working in powered land and brownfields, it is one of the most compelling regions in the country.

TVA (Tennessee Valley Authority)

The Tennessee Valley Authority is the federal power utility serving Tennessee and parts of Alabama, Mississippi, Kentucky, Georgia, North Carolina, and Virginia. TVA operates a large, diversified generation fleet (nuclear, hydro, gas, and more), historically offers competitive rates, and has actively courted large industrial and data center load. A single utility covering a broad, power-rich region simplifies the development conversation and is a major reason the area attracts compute.

Power availability

TVA's generation base and transmission network give the region meaningful capacity to serve large new load — the scarcest resource in the industry. Combined with retired and retiring coal plants in the footprint (with their existing interconnections), Tennessee offers both grid power and brownfield power opportunities.

Water availability

The region is comparatively water-rich — major rivers, reservoirs, and in West Tennessee the Memphis Sand aquifer. For an industry where water can be a constraint elsewhere (notably the desert Southwest), reliable water is a genuine competitive advantage for cooling.

Central geography

Tennessee's central US location offers low latency to a large share of the population and proximity to multiple major markets — useful for both content distribution and latency-sensitive inference. It also sits on major logistics and transportation corridors.

Fiber routes

Major long-haul fiber routes cross the state, following its interstate and rail corridors and connecting Southeast and Midwest markets. Good connectivity plus good power is the combination data centers seek.

The four metros

Memphis

Power, water (aquifer), logistics hub, industrial land, fiber and rail — and a magnet for very large AI projects. Arguably the headline Tennessee market.

Nashville

Fast-growing economy and tech presence, central geography, TVA power, strong connectivity — a rising hub with deep labor and capital.

Knoxville

Near TVA headquarters and Oak Ridge's research and energy ecosystem; access to power, water, and a technical workforce.

Chattanooga

Famous for its municipal gigabit fiber network ("Gig City"); strong connectivity, power, and a growing tech identity.

The local advantage: Tennessee combines TVA power, water, central geography, and fiber with a stock of industrial brownfields — including retiring coal assets — sitting on existing interconnections. For developers, investors, and landowners who understand powered land, that overlap is the opportunity. Knowing the local utility relationships, sites, and incentive landscape is where edge is built.
eXp Commercial · Passive Investments

Have land near power — or looking for a data center site?

Carson Jones is a licensed commercial real estate advisor and business broker with eXp Commercial. If you own acreage near transmission, a substation, or a brownfield, or you're sourcing powered land for development, get a straight read on what your site is worth and who's buying.

Visit Passive Investments →

Chapter 12 — How Investors Underwrite Data Center Land

Underwriting data center land is fundamentally an exercise in risk decomposition. The headline numbers — price per acre, price per megawatt — are downstream of a series of risks that determine whether a site can actually become a revenue-producing campus. Sophisticated investors price each risk explicitly.

Power Risk

The dominant risk. Can the site obtain the required megawatts, at an acceptable cost, on the needed timeline? This means examining the serving utility's available capacity, transmission proximity, substation access, interconnection queue position, and the credibility of any power commitment. A site without a clear, credible path to power is not a data center site at any price — it is a speculation on getting power. Underwriting assigns this the heaviest weight.

Entitlement Risk

Will the project get the zoning, permits, and approvals it needs, and on what timeline? Sites already zoned industrial or for data center use, in cooperative jurisdictions, carry low entitlement risk. Sites requiring rezoning, variances, or contentious hearings carry more. Entitlement certainty has direct value because it removes a slow, binary risk.

Utility Risk

Beyond raw power availability, this captures the reliability, rate structure, and behavior of the utility — rate increases, large-load tariffs, the terms of interconnection agreements, who pays for upgrades, and the utility's track record of delivering on commitments. Utility risk also includes water and gas service for cooling and on-site generation.

Construction Risk

Can the campus be built on budget and on schedule? This covers site conditions (topography, soils, environmental remediation), supply chain for critical gear (transformers and switchgear have had long lead times), labor availability, and contractor capacity. Brownfields add demolition and remediation to the construction-risk column.

Tenant Risk

Who will lease or buy the capacity, and how creditworthy and committed are they? Hyperscale tenants are exceptionally creditworthy, but their site requirements are demanding and their decisions can move. Underwriting considers the depth of demand in the market, the likelihood of securing a tenant, lease term and structure, and the credit behind the cash flow.

Exit Risk

How and to whom does the investment ultimately monetize — a sale of powered land to a developer, a stabilized leased asset sold to an institutional buyer, or a long-term hold? Exit risk weighs liquidity, the buyer universe, cap-rate sensitivity, and how durable the asset's advantages (power, location, tenant) will be at sale. The more transferable the site's core advantages, the lower the exit risk.

RiskCore questionMitigants investors look for
PowerCan we get the MW, when, at what cost?Existing substation/interconnection, transmission proximity, signed utility commitment, behind-the-meter option
EntitlementWill it be approved, and how fast?Existing industrial/data-center zoning, cooperative jurisdiction, prior approvals
UtilityAre rates/terms/reliability acceptable?Clear tariff, favorable interconnection agreement, strong utility track record
ConstructionOn budget and on time?Clean geotech, secured long-lead equipment, available labor, defined remediation
TenantWho pays, how strong, how committed?Investment-grade tenant, signed lease/LOI, deep market demand
ExitHow do we monetize?Broad buyer pool, transferable power/location advantages, stabilized cash flow

Chapter 13 — Data Center Economics

Data center economics revolve around a handful of metrics that translate physical capacity into financial returns. Understanding them lets you compare deals, gauge development profit, and see why the asset class attracts so much capital. (Figures are general industry ranges and vary widely by market, design, and time.)

Cost per MW

Cost per megawatt is the headline development metric — the all-in cost to build a megawatt of critical IT capacity, including building, power, and cooling infrastructure. Industry figures commonly fall in the range of roughly $7M–$15M per MW for shell-and-core through fully fitted capacity, varying with tier, density, cooling type, and location. Because capacity is leased by the megawatt, cost per MW versus rent per MW drives the return.

Cost per rack

Cost per rack expresses cost at the rack level. As rack densities climb (from ~10 kW toward 100 kW+), the cost and complexity per rack rise — especially for the power distribution and liquid/immersion cooling that high density requires. Density changes the math: a high-density hall fits more compute (and more revenue) into the same building footprint, but at higher per-rack infrastructure cost.

Cost per square foot

Cost per square foot is the traditional real estate metric, but it is secondary in data centers because value tracks power, not floor area. A small, ultra-dense AI hall can be worth far more than a large, low-density one. Cost per square foot is still used for the building shell, but megawatts are the true unit of account.

Yield on cost

Yield on cost (development yield) is stabilized net operating income divided by total development cost. It measures the return the developer creates by building. Comparing yield on cost to the cap rate at which the stabilized asset can be sold reveals the value created — the heart of the development case.

Development spreads

The development spread is the gap between yield on cost and the market exit cap rate. If a developer builds to, say, an 8% yield on cost and the stabilized asset trades at a 6% cap rate, that 200-basis-point spread is the profit margin of development, capitalized into value. Wide spreads — driven by scarce powered land and strong tenant demand — are exactly what is attracting developers and capital to the sector.

Why land basis matters so much: in a powered-land deal, controlling the dirt and the power early — at a low basis — is what creates the spread. The investor who secures shovel-ready powered land before the market fully prices the power is positioned to capture the repricing as demand arrives. That is the land-basis thesis at the center of this whole guide.
Land & site~5–15%
Building shell & fit-out~25–40%
Power & electrical infrastructure~25–40%
Cooling & mechanical~15–25%

Illustrative share of total data center development cost by category. Power and cooling together often rival or exceed the building itself — a reminder that a data center is an electrical asset wearing a building.

Chapter 14 — The AI Infrastructure Buildout

The current cycle is best understood as the construction of an entirely new layer of industrial infrastructure — "AI factories" — at a pace and scale rarely seen. The numbers being committed by the largest players dwarf prior data center cycles.

AI factories

The term AI factory captures the idea that these facilities are industrial plants that manufacture intelligence — taking in electricity and data and producing trained models and inference at scale. Unlike traditional data centers optimized for many small workloads, AI factories are purpose-built around dense accelerator clusters and the extreme power and cooling they demand. They represent a new building typology, not just a bigger data center.

GPU clusters

At the heart of every AI factory are GPU clusters — thousands of accelerators networked to train and serve models. The size of these clusters keeps growing, and each generation tends to demand more power per chip and per rack. The cluster's power and networking requirements dictate the building's electrical and cooling design, which is why hardware roadmaps drive real estate decisions.

Inference facilities

Inference facilities serve trained models to users. As AI moves from training breakthroughs to mass deployment, inference demand scales with usage and is expected to become the larger long-run share of compute. Because inference is more latency-sensitive, it distributes capacity toward population centers and the edge, complementing the remote, power-rich training campuses.

Future demand

Projections for AI-driven power and capacity demand are large and rising, and while specific forecasts differ and will change, the direction is consistent: continued, substantial growth in compute, power, and the physical infrastructure to house it. The binding constraint on that growth is increasingly power and grid capacity — which loops directly back to the central thesis of this guide.

The key players

NVIDIA

The dominant maker of AI accelerators. Its hardware sets the power density and cooling requirements that every AI facility must engineer around — making NVIDIA's roadmap a de facto blueprint for data center design.

OpenAI

A leading AI lab whose models drove the consumer AI moment; its compute needs — and partnerships to build out massive capacity — are a major demand driver.

xAI

An AI company notable for standing up very large GPU clusters rapidly, including projects that lean on on-site/behind-the-meter generation to bypass grid constraints.

Around these sit the hyperscalers (AWS, Microsoft, Google, Meta, Oracle) who build or lease the capacity, the colocation developers who deliver much of it, and the utilities and power developers racing to feed it. The AI buildout is, at bottom, a power-and-real-estate story — which is why landowners, developers, and investors who understand powered land are positioned at the center of it.

Chapter 15 — Data Center FAQs (150+)

A comprehensive, answer-engine-optimized question bank covering land, power, brownfields, water, fiber, economics, markets, and process. Each answer is self-contained so it can stand alone in search and AI results.

Land & Site Basics

What is data center land?
Data center land is real estate suitable for building a data center — most importantly, land that can be served with large amounts of reliable electrical power, and that also offers adequate acreage, buildable topography, low flood risk, fiber connectivity, water for cooling, and appropriate zoning. The defining feature is power availability, which is why the term often overlaps with "powered land."
What is powered land?
Powered land is land that has secured access to substantial electrical capacity — through an existing substation, transmission proximity, a utility commitment, or interconnection rights — making it ready (or nearly ready) to support a data center. Because power is the binding constraint, powered land commands a premium far above comparable unpowered ground.
How much land does a 100 MW data center require?
It varies with design and density, but a 100 MW facility might occupy on the order of 20–100+ acres, accounting for the building(s), substation, generators, cooling plant, security setbacks, and room for expansion. Single-story, lower-density, generator-heavy designs use more land; dense, multi-story designs use less. Campuses planning multiple phases acquire far more.
How many acres does a hyperscale campus need?
Hyperscale campuses commonly assemble 100–1,000+ acres to accommodate multiple large buildings, on-site substations and possibly generation, cooling infrastructure, setbacks, and future phases. Large contiguous tracts are strongly preferred so the campus can grow without fragmentation.
Why does contiguous acreage matter?
Contiguous, unbroken land allows efficient campus layout, phased expansion, and consolidated infrastructure. Acreage split by roads, easements, creeks, or separate parcels is harder to develop and worth less, even at the same total size. Assembling contiguous tracts is a core part of data center land work.
What kind of topography do data centers need?
Flat to gently sloping, well-drained land is ideal. It minimizes grading, earthwork, and foundation costs and allows efficient building pads and equipment yards. Steep slopes, rock, and irregular terrain raise costs and can sterilize portions of a site.
Can a data center be built in a flood zone?
It is strongly disfavored. Data centers are mission-critical and cannot tolerate flooding, so FEMA floodways and high-risk flood zones are generally disqualifying. Even partial flood exposure complicates insurance, financing, and tenant approval. Sites well above flood risk are a baseline requirement.
What makes a site "shovel ready"?
A shovel-ready site has its entitlements, zoning, environmental clearances, and utility commitments in place so construction can begin with minimal delay. When secured power is added, it becomes "shovel-ready powered land" — the most valuable raw input in the industry because it removes the two slowest risks: entitlement and power.
What zoning do data centers require?
Typically industrial zoning or a purpose-built data center designation. Sites already appropriately zoned, in cooperative jurisdictions, are worth more than those needing rezoning, variances, or contentious public hearings. Entitlement certainty meaningfully de-risks a project.
How far from a city should a data center be?
It depends on the workload. Latency-tolerant AI training campuses can sit far from population centers in power-rich rural areas. Latency-sensitive inference, edge, and interactive workloads need to be closer to users. Many large campuses deliberately locate in rural areas with power and land, away from congested metros.
What is the difference between greenfield and brownfield data center sites?
A greenfield is undeveloped land with no prior industrial use; a brownfield is a previously developed industrial site, often with existing power, utilities, and zoning (and sometimes contamination). Greenfields are cleaner but slower to power; brownfields can come with existing interconnection and zoning, which is increasingly decisive.
How much does data center land cost?
There is no single figure — it ranges from modest rural land prices to very high per-acre values for prime powered sites in established markets. The key driver is not location in the traditional sense but power: a site with secured large-scale power can be worth many multiples of the same acreage without it.
What is an option or land bank in data center development?
Developers often control land via options (the right to buy within a window) or land banking (holding land for future development) rather than buying outright immediately. This lets them secure control while pursuing power and entitlements, limiting capital at risk until the site is proven powerable.

Power, Megawatts & the Grid

How much power does a data center need?
Anywhere from under 1 MW for small edge/enterprise sites to 50–150 MW for a hyperscale building or phase, up to 500 MW–1 GW+ for large AI/cloud mega-campuses. AI workloads have pushed per-facility power dramatically higher than the prior cloud-era norm.
What is a megawatt and why is it the key metric?
A megawatt is one million watts of power. It is the key metric because data center capacity, leases, and value are all denominated in megawatts of critical IT load, not square feet. The industry's defining question is "how many megawatts can this site deliver, and when."
Why does power matter more than land?
Land is abundant and relatively cheap; deliverable, reliable, near-term power is scarce, expensive, and slow to obtain. A site can be graded in months, but a new interconnection and substation can take years and large capital. So value, risk, and competitive advantage all migrate to whoever can deliver megawatts.
What is an interconnection queue and why is it backed up?
It is the line of projects waiting for the studies and approvals to connect new load or generation to the grid. Queues have congested because demand (data centers, electrification, renewables) has outpaced the studies, transmission upgrades, and utility capacity needed to process and serve it, producing multi-year waits in many regions.
How long does it take to get power to a data center site?
It varies widely. Where existing substation and transmission capacity is available, power can be arranged relatively quickly. Where new transmission, substations, or generation are required, timelines of several years are common. This is why sites with existing interconnection — like brownfields and retired plants — are so valuable.
What utilities do data centers require?
Primarily large-scale, reliable electricity. They also need water or another cooling medium, telecommunications/fiber, and increasingly natural gas where on-site generation is planned. Sewer and stormwater management round out the list. Of these, electric power is by far the dominant and most constraining requirement.
What is a substation and why does a data center need one?
A substation transforms high-voltage transmission power down to usable levels and is the connection point to the grid. A data center either ties into an existing substation with available capacity or builds a new one. Existing substation capacity near a site is one of the most valuable attributes it can have.
What is a switchyard?
A switchyard is the high-voltage area — often at a power plant or large substation — where transmission lines connect, switch, and are protected. Retired power plants frequently retain valuable switchyards and transmission ties, a major reason their sites are coveted for data centers.
How close does land need to be to transmission lines?
Closer is better and cheaper. Every mile of new high-voltage line to reach a site adds cost, time, and permitting risk. Sites adjacent to or very near high-capacity transmission (and a substation) have a far shorter, cheaper path to large power. The required distance depends on the voltage and spare capacity of nearby lines.
What voltages are typical for data center power?
Bulk transmission near large data centers often runs at 115 kV, 138 kV, 230 kV, 345 kV, or 500 kV, stepped down through a substation. Higher-voltage transmission can move more power, so proximity to high-voltage lines with spare capacity supports larger loads.
What is behind-the-meter generation?
It is power generated on-site, on the customer's side of the utility meter — such as natural gas turbines, fuel cells, solar, or future small modular reactors — allowing a data center to come online without waiting for grid interconnection. It is a leading strategy in the current power-constrained environment.
Why are data centers turning to natural gas?
On-site natural gas generation can bring large blocks of power online relatively quickly where gas pipelines exist, bypassing congested interconnection queues. It serves as a bridge (or primary) power source for AI campuses that cannot wait years for the grid, though it carries emissions and permitting considerations.
Can data centers be powered by nuclear?
Yes — and it is a growing strategy. Options include co-locating at existing nuclear plants, restarting retired reactors, and future small modular reactors (SMRs). Nuclear offers large, firm, carbon-free power, and several major operators have signed nuclear-related deals, signaling willingness to underwrite new firm generation.
What are small modular reactors (SMRs)?
SMRs are smaller, factory-built nuclear reactors designed to be deployed more quickly and flexibly than traditional large plants. They are seen as a potential source of firm, carbon-free power co-located with data centers. The technology is still maturing and commercial deployment timelines remain uncertain, but interest is significant.
How does a 1 GW data center get its power?
At gigawatt scale, existing grid capacity is rarely sufficient, so developers typically must arrange new generation — large-scale gas, nuclear, or major transmission and substation buildouts — often combining grid power with behind-the-meter generation. A 1 GW campus is a city-scale load and an energy project as much as a real estate project.
Does AI use more power than traditional computing?
Yes, dramatically. AI training racks can draw 40–130 kW or more versus 5–10 kW for traditional racks, and AI campuses can demand hundreds of megawatts to over a gigawatt. This step-change in density and total load is the central reason power has become the industry's binding constraint.
What is rack density and why is it rising?
Rack density is the amount of power (and heat) per rack. It is rising because AI accelerators pack far more compute — and power draw — into each unit than prior hardware. Higher density drives the shift from air cooling to liquid and immersion cooling and reshapes building electrical and mechanical design.

Reliability & Design

What is N+1 redundancy?
N+1 means having the components needed to carry the load (N) plus one spare, so a single failure or maintenance event does not interrupt operations. If four cooling units are needed, N+1 installs five. It is a common, cost-effective reliability standard.
What is 2N redundancy?
2N means fully duplicating the infrastructure — two complete, independent systems — so an entire side can fail and operations continue on the other. It is more expensive than N+1 but offers higher fault tolerance, used in mission-critical, high-tier facilities.
What are data center tiers (I–IV)?
Tiers classify reliability from Tier I (basic, no redundancy) to Tier IV (fault-tolerant, fully redundant, highest uptime). Higher tiers mean more redundant power and cooling, higher cost, and stronger availability guarantees. Tenants pick a tier based on how critical their workloads are.
What is PUE?
Power Usage Effectiveness is total facility power divided by IT power. A PUE of 1.5 means half a watt of overhead per watt to servers; 1.0 is perfect. Efficient modern facilities target well below 1.3. Lower PUE means lower operating cost and is a key efficiency benchmark.
What is a powered shell?
A powered shell is a building delivered with structure, power, and cooling infrastructure in place but the IT-specific interior left for the tenant to fit out. It speeds deployment versus ground-up construction while letting tenants customize the interior, and is a common developer product.
What backup power do data centers use?
Traditionally diesel generators paired with uninterruptible power supplies (UPS, often batteries) bridge the gap during outages. Newer approaches include natural gas generation, fuel cells, and large battery systems. Backup capacity and redundancy level depend on the facility's tier and tenant requirements.

Brownfields & Coal Plant Conversion

What is a brownfield?
A brownfield is a previously developed industrial or commercial site that is idle or underused, often with real or perceived environmental contamination — for example a retired power plant, closed factory, or old mill. For data centers, brownfields often come with existing power, utilities, and industrial zoning.
Can a brownfield become a data center?
Yes — and brownfields are among the most sought-after data center sites precisely because they often arrive with existing power infrastructure, industrial zoning, utility connections, and large contiguous land. The trade-off is potential remediation, demolition, and verification of the actual usable capacity of existing infrastructure.
Why do data centers love retired coal plants?
When a coal plant retires, its generation goes away but its grid interconnection — the high-voltage switchyard and transmission ties — remains, along with cooling-water access, rail, and large acreage. A data center can import large load through that existing interconnection, saving years and large capital versus a greenfield. That makes coal-plant sites extraordinarily valuable.
What other industrial sites convert well to data centers?
Steel mills (massive electrical service, heavy foundations, rail), paper mills (abundant water rights and power), and large manufacturing facilities (power, utilities, contiguous land) all convert well. The common thread is existing heavy power and utility infrastructure plus industrial zoning.
Why might a coal plant site be worth more as a data center than as industrial land?
Sold as generic industrial land, the site trades at industrial-acre pricing minus demolition and remediation. But to a data center developer, the existing interconnection and substation can be worth more than the land itself, because the alternative is a multi-year wait and nine-figure infrastructure spend on a greenfield. That gap is the brownfield opportunity.
What are the risks of brownfield data center development?
Environmental remediation, demolition costs, the actual condition and usable capacity of "existing" aged infrastructure, clear title to interconnection rights, and possible community or regulatory considerations. The thesis is powerful but each item must be verified with environmental and engineering diligence, not assumed.
What is an environmental Phase I and Phase II assessment?
A Phase I Environmental Site Assessment reviews a property's history and conditions to identify potential contamination, without sampling. If concerns surface, a Phase II involves actual sampling and testing of soil, groundwater, or materials. Both are standard diligence on brownfields and many data center sites.
Does existing infrastructure on a brownfield always work for a data center?
Not automatically. Existing substations, transmission ties, and water intakes may be aged, undersized, or require upgrades, and interconnection rights may need to be re-established or transferred. The value is real but must be engineered and verified; "existing" is a starting point, not a guarantee of usable capacity.
How do you determine the highest and best use of an obsolete industrial site?
Test each candidate use against four filters: legally permissible (zoning, entitlements, deed), physically possible (acreage, topography, infrastructure), financially feasible (value versus conversion, demolition, and remediation cost), and maximally productive (which qualifying use yields the most value). For many powered brownfields the answer is a data center; for well-located paved yards it may be industrial outdoor storage (IOS) or enterprise IOS (EIOS). The key is to test uses rather than default to the property's prior life.
What are the signs my industrial property is worth more than its current use?
Strong signals include: proximity to high-voltage transmission or a substation; large existing electrical service; being a retired power plant, steel mill, or paper mill; large contiguous acreage; water rights or a permitted intake; nearby long-haul fiber; direct highway, interchange, or rail access; existing industrial zoning; location in an Opportunity Zone or incentive-rich jurisdiction; and being already paved, fenced, and stabilized for IOS/EIOS use. Three or more of these often means the highest and best use — and the value — is well above the current use.
How do you sell an industrial campus to institutional buyers?
Establish the highest and best use first, then assemble a credible power and infrastructure story, de-risk diligence up front (Phase I/II, survey, title, zoning), confirm entitlements and community posture, build a professional data room, reach the specialized buyer universe (hyperscalers, data center developers, REITs, infrastructure funds), and structure the deal — options, phased takedowns, longer diligence — to match how institutional buyers underwrite. Institutional buyers pay for certainty and discount ambiguity, so removing ambiguity before going to market defends and raises price.

Opportunity Zones & Incentives

What is an Opportunity Zone?
An Opportunity Zone is a federally designated economically distressed area where investors can receive capital-gains tax benefits for long-term investment made through a Qualified Opportunity Fund. The program is designed to channel capital into distressed communities. Specific rules and timelines have evolved and should be confirmed with a tax advisor.
Can a data center be built in an Opportunity Zone?
Yes. Data centers are capital-intensive, long-hold assets — the profile the program rewards — and many Opportunity Zones sit in rural or post-industrial areas where powered land and brownfields are found. Pairing the asset with the tax structure can be powerful, subject to current OZ rules and professional tax advice.
What are the tax benefits of Opportunity Zone investment?
Generally, deferral of tax on capital gains rolled into a Qualified Opportunity Fund, and potential exclusion of tax on the appreciation of the OZ investment if held long term (around ten years). Exact percentages, dates, and rules have changed over time, so confirm current terms with qualified tax counsel before relying on them.
Why are Opportunity Zones a good fit for data centers?
Because the largest OZ benefit rewards long holds, which aligns with the long duration of data center ownership and leases; and because many zones are rural and power-rich, overlapping with the best powered-land and brownfield sites. The asset economics, the tax policy, and the community-development purpose can point the same direction.
What tax incentives do states offer for data centers?
Commonly sales-and-use tax exemptions on servers and equipment, property-tax abatements, and sometimes income or utility-tax incentives, often tied to investment and (modest) job thresholds. These can swing project economics meaningfully and are a genuine site-selection factor; programs vary widely by state and locality.

Water & Cooling

How much water does a data center use?
It depends entirely on cooling design. Evaporative cooling can use large volumes; air-cooled (dry) designs use little to none but consume more energy; closed-loop liquid and immersion cooling can sharply reduce water use. Large evaporatively cooled facilities can consume water comparable to a sizeable population, which is why design and water strategy matter.
Why do data centers use water?
To remove the substantial heat generated by computing equipment efficiently. Water carries heat far more effectively than air, so water-based cooling has historically been energy-efficient. The trade-off is water consumption, which has become a public concern, pushing the industry toward lower-water designs.
What is the difference between air, liquid, and immersion cooling?
Air cooling uses fans and chillers to cool room air (low water, higher energy). Liquid cooling brings coolant directly to the chips for far better heat removal at high density. Immersion cooling submerges servers in non-conductive fluid for the highest density and efficiency. AI hardware is driving adoption of liquid and immersion.
Can data centers be built without using much water?
Yes. Air-cooled (dry) designs, closed-loop liquid cooling, and immersion cooling can dramatically cut or nearly eliminate water consumption, often by trading some energy efficiency for water savings. Using reclaimed or non-potable water is another common strategy, especially in water-scarce regions.
What is WUE?
Water Usage Effectiveness measures water consumed relative to IT energy use, typically in liters per kilowatt-hour — the water analog of PUE. Operators increasingly track and disclose WUE, and low-water designs aim to push it toward zero.
Why is data center water use controversial?
Because a large facility's water demand can rival a sizeable community's, raising concerns about capacity, drought resilience, and fairness to other users — especially in arid regions. Developers address this with non-potable/reclaimed water, closed-loop or dry cooling, and transparency about consumption.

Fiber & Connectivity

What is dark fiber?
Dark fiber is fiber-optic cable that has been installed but is not yet "lit" with active equipment — spare capacity in the ground. Access to dark fiber lets an operator light its own dedicated, high-capacity connections quickly and cost-effectively, without waiting for a carrier to build new routes.
Why is fiber connectivity important for data centers?
A data center must move enormous amounts of data to and from users and other facilities. Abundant, diverse, high-capacity fiber connectivity makes that possible and reliable. Power lets a data center run; fiber lets it serve its purpose. Poor connectivity can disqualify an otherwise good site.
What is a long-haul network?
Long-haul fiber networks carry traffic between cities and regions over long distances. Proximity to multiple long-haul routes gives a data center diverse, high-capacity paths to the rest of the internet. These routes often parallel highways, rail, and pipelines.
What is a carrier hotel?
A carrier hotel is a major interconnection facility where many networks meet and exchange traffic. Being near or on a route to a carrier hotel improves a data center's connectivity options and lowers the cost of reaching many networks at once.
What is fiber redundancy?
Fiber redundancy means having multiple, physically diverse fiber paths so a single cut cannot sever the facility. Multiple carriers entering from different directions along separate rights-of-way is the gold standard, paralleling the redundancy required for power.
What is latency and why does it matter?
Latency is the delay for data to travel to and from a facility. It is critical for real-time and interactive workloads (inference, gaming, trading) and largely irrelevant for latency-tolerant ones (AI training). Matching a site's location and connectivity to the intended workload is part of good underwriting.

Economics & Underwriting

How do you underwrite data center land?
By decomposing and pricing risks: power risk (can the MW be delivered, when, at what cost), entitlement risk, utility risk, construction risk, tenant risk, and exit risk. Power risk dominates. The headline price metrics — per acre, per megawatt — are downstream of how those risks resolve.
What is cost per MW?
The all-in cost to build a megawatt of critical IT capacity, including building, power, and cooling. Industry figures commonly fall around $7M–$15M per MW depending on tier, density, cooling type, and location. Because capacity is leased by the megawatt, cost per MW versus rent per MW drives returns.
What is yield on cost?
Yield on cost (development yield) is stabilized net operating income divided by total development cost. It measures the return created by building. Comparing it to the exit cap rate reveals the value development creates — the core of the development case.
What is a development spread?
The development spread is the gap between yield on cost and the market exit cap rate. Build to an 8% yield and sell at a 6% cap, and that 200-basis-point spread is the development profit capitalized into value. Wide spreads — from scarce powered land and strong demand — are drawing capital into the sector.
Why is cost per square foot less important for data centers?
Because data center value tracks power, not floor area. A small, ultra-dense AI hall can be worth far more than a large, low-density one. Cost per square foot is used for the building shell, but megawatts are the true unit of account.
Who are the tenants for data centers?
Primarily hyperscale cloud and AI operators (AWS, Microsoft, Google, Meta, Oracle), colocation providers who sublease to many customers, large enterprises, and AI companies. Hyperscale tenants are exceptionally creditworthy, which supports long-duration, low-risk cash flows once leased.
How long are data center leases?
Wholesale and hyperscale data center leases are typically long-term — often 10–15 years or more, frequently with renewal options and escalations. Long terms backed by strong-credit tenants are part of what makes stabilized data center assets attractive to institutional buyers.
What returns do data center investments target?
Returns vary by strategy and risk. Development (building powered capacity) targets higher returns reflecting power, entitlement, and construction risk; stabilized leased assets trade at lower cap rates reflecting strong-credit, long-duration cash flow. The development spread between the two is where much of the value is created. Specific targets are deal- and market-specific.
What is the land-basis thesis in data centers?
It is the idea that controlling powerable land at a low basis — before the market fully prices the power — positions an investor to capture the repricing as demand arrives. Securing shovel-ready powered land early is what creates the development spread and much of the upside.
Why are data centers attractive to investors right now?
Because demand (driven by AI and cloud) is strong and growing, tenants are highly creditworthy, leases are long, and supply is constrained by power — creating wide development spreads and scarcity value for powered land. The constraint that makes development hard is the same one that makes secured power valuable.

Markets & Geography

What are the biggest data center markets in the US?
Northern Virginia (Ashburn/"Data Center Alley") is the largest, followed by markets like Dallas, Phoenix, Atlanta, Chicago, Silicon Valley, and the Pacific Northwest, with fast-growing emerging markets including Tennessee (Memphis, Nashville), Ohio, and others. Growth is shifting toward power-rich, land-rich regions.
Why is Ashburn, Virginia so dominant?
Decades of fiber infrastructure, a deep operator ecosystem, and proximity to a major internet interconnection point made Northern Virginia the default. Its challenge now is its own success — scarce, expensive power and land and grid strain — which is pushing new development toward emerging markets.
Why is the data center market shifting to the Southeast?
Because established markets are hitting power and land limits, demand spills into regions with available power, land, water, incentives, and central geography. The Southeast — including the TVA footprint, Georgia, and the Carolinas — offers exactly that combination.
Why is Phoenix popular despite water scarcity?
Large available land, low natural-disaster risk, strong incentives, and aggressive utility support make Phoenix attractive. Water scarcity is the key watch-out, which is why air-cooled and closed-loop designs and careful water strategy are especially important there.
Why is Tennessee emerging as a data center market?
It combines TVA power, abundant water, central US geography, strong fiber routes, business-friendly policy, and a stock of industrial brownfields (including retiring coal assets) with existing interconnections. That overlap of power, water, location, and convertible sites is unusually strong.
What role does the TVA play?
The Tennessee Valley Authority is the federal utility serving Tennessee and parts of six neighboring states, with a large diversified generation fleet and historically competitive rates. A single utility covering a broad, power-rich region simplifies large-load development and is a major reason the area attracts data centers.
Why does Memphis attract large AI projects?
Memphis offers TVA power, abundant water from the Memphis Sand aquifer, a central logistics location, available industrial land, and major fiber and rail infrastructure. That mix of power, water, and land has drawn significant attention, including very large AI developments.

Process, Construction & Operations

How long does it take to build a data center?
Once power and entitlements are secured, building a facility can take roughly 1–3 years depending on size, phasing, and the supply of long-lead equipment like transformers and switchgear. The slowest part is often not construction but securing power and approvals beforehand.
What are long-lead items in data center construction?
Critical electrical equipment — large transformers, switchgear, generators, and increasingly specialized cooling gear — has had extended lead times, sometimes well over a year. Securing this equipment early is a key part of de-risking construction schedules.
How many jobs does a data center create?
Construction is labor-intensive and can employ hundreds to thousands temporarily, but ongoing operations typically require relatively few staff — often dozens — because facilities are highly automated. The economic benefit to communities comes more from capital investment and property-tax base than from operating headcount.
Do data centers benefit local communities?
They can add substantial property-tax base and capital investment, often on land (like brownfields) that was previously tax-dormant, with modest demand on schools or traffic. Trade-offs include power and water demand and limited permanent jobs. Net impact depends on incentives granted, the site, and how the project is structured.
What permits does a data center need?
Typically zoning/land-use approval, building and electrical permits, environmental permits (stormwater, air permits for generators, wetlands where relevant), water and sewer approvals, and utility/interconnection agreements. Brownfields may add remediation-related approvals. Requirements vary by jurisdiction.
What is a hyperscaler?
A hyperscaler is a very large cloud or internet company — such as AWS, Microsoft, Google, Meta, or Oracle — that operates at massive scale and builds or leases hyperscale data center capacity. Hyperscalers are the dominant tenants and developers driving the powered-land market.
What is wholesale colocation?
Wholesale colocation leases large, dedicated blocks of power and space (often entire data halls) to single large customers, frequently hyperscalers supplementing their own builds. It contrasts with retail colocation, which rents smaller racks or cages to many tenants.
What is retail colocation?
Retail colocation rents smaller increments of space and power — racks, cages, or partial rooms — to many different customers who place their own equipment in a shared facility. It serves enterprises and smaller operators needing professional data center space without building their own.
What is an AI factory?
"AI factory" describes a facility purpose-built to train and serve AI models at industrial scale — taking in electricity and data and producing intelligence. These are organized around dense accelerator clusters and the extreme power and cooling they require, representing a new building typology distinct from traditional data centers.
What is a GPU cluster?
A GPU cluster is a large group of graphics/accelerator processors networked together so thousands of chips operate as a single machine to train or serve AI models. These clusters are the densest, most power-hungry hardware deployed at scale and dictate a facility's electrical and cooling design.
What role does NVIDIA play in data center design?
NVIDIA is the dominant maker of AI accelerators, and its hardware sets the power density and cooling requirements that AI facilities must engineer around. In effect, NVIDIA's hardware roadmap functions as a blueprint that shapes how AI data centers are built.
Will AI demand for data centers continue to grow?
Forecasts vary and will change, but the consistent direction is continued substantial growth in compute, power, and the infrastructure to house it, driven by AI adoption layered on top of cloud, digital transformation, autonomy, robotics, defense, and healthcare. The binding constraint on that growth is increasingly power and grid capacity.
What is the biggest risk to the data center boom?
The most cited constraints are power and grid capacity — the ability to deliver enough reliable electricity fast enough — along with water in some regions, supply-chain limits on critical equipment, community and regulatory pushback, and the possibility that AI demand growth moderates. Power availability is both the constraint and the opportunity.
How can a landowner tell if their land is good for a data center?
The first questions are about power: how close is high-voltage transmission and a substation with capacity, and what does the serving utility say about available load? Then acreage and contiguity, topography, flood risk, environmental condition, fiber proximity, water, zoning, and incentives. Land near transmission, substations, or a brownfield with existing power is the strongest candidate.
How do developers control land before committing capital?
Often through purchase options or land banking, which secure the right to buy within a window while the developer pursues power studies, interconnection, and entitlements. This limits capital at risk until the site is proven powerable, then converts to purchase once the key risks are resolved.
What does "the new currency is power" mean?
It means electricity has replaced location as the scarce, value-defining resource in data center real estate. Because reliable near-term power is hard to obtain while land is abundant, whoever controls or can deliver megawatts controls the deal — so power, not acreage, is the true currency of the asset class.
A developer contacted me about my land. Should I hire my own advisor before negotiating?
Yes, and do it before you respond in any detail. The party approaching you does this for a living and you likely do not, and the first document they send is usually an option or letter of intent that quietly sets price, diligence period, extensions, and who controls the entitlement process. A broker or attorney who has done data center land deals will tell you what the parcel is actually worth to a developer given its power position, which is frequently a different number than what raw acreage comps suggest. The fee is small against the spread.
How do I know whether the price offered for my land is fair?
Agricultural or raw land comps are the wrong benchmark, because a developer is not buying dirt, they are buying a power position and an entitlement path. Value tracks proximity to high-voltage transmission and a substation with real available capacity, interconnection queue position, zoning, contiguous usable acreage, water, and fiber. A parcel with a viable near-term interconnect can be worth a large multiple of neighboring farmland, and one without power may be worth ordinary land value no matter how large it is. Price it against what makes the site work, not against the field next door.
What does a data center land option actually pay me while my property is tied up?
Typically a modest non-refundable option payment for an initial term, often a year or two, with extension payments if the developer needs longer, and those payments may or may not credit against the purchase price. Negotiate three things carefully: how long the total tie-up can run with all extensions exercised, whether extension payments escalate, and what happens to your ability to farm, lease, or otherwise use the land during the option period. A long option at a low payment transfers a lot of optionality to the developer for very little.
Is buying land next to an announced data center a good play?
Sometimes, but the thesis has to be more specific than proximity. Adjacent land only appreciates if it can serve the ecosystem the campus creates: additional phases for the same developer, substation or transmission easements, contractor laydown and staging during a multi-year build, or workforce-serving uses. Land that cannot get power, is too small to matter, or sits on the wrong side of a road can stay exactly what it was. Check the utility's capacity plans for the corridor before assuming the neighbor's announcement prices your parcel.
How much local opposition should I expect if I sell farmland to a data center developer?
Plan for it. Opposition around large projects now routinely centers on water use for cooling, noise from generators and chillers, transmission line routing and the eminent domain that sometimes accompanies it, and the loss of farmland itself. Rezoning and conditional use hearings are where that shows up, and a contested approval can add many months. Talk to your neighbors before the public hearing rather than after, and make sure your contract puts entitlement risk and timeline on the developer rather than leaving you tied up while they fight it out.

Chapter 16 — Future Trends Through 2035

The next decade will be defined by the race to feed compute with power. The trends below are already underway and are likely to intensify as AI scales and the grid struggles to keep pace.

Nuclear-powered data centers

Expect nuclear to move from novelty to mainstream strategy for the largest operators. Co-location at existing nuclear plants, restarts of retired reactors, and long-term power agreements give hyperscalers large, firm, carbon-free power that the congested grid cannot quickly provide. The willingness of major players to underwrite nuclear signals how valuable firm power has become.

Small modular reactors (SMRs)

SMRs — smaller, factory-built reactors — are a leading bet for delivering firm power co-located with data centers. Commercial timelines remain uncertain and the technology is still maturing, but the level of interest and investment suggests SMRs could become a meaningful part of the power mix for compute in the latter half of the decade.

Natural gas generation

In the near term, on-site natural gas is the pragmatic bridge. Where pipelines exist, gas can bring large blocks of power online far faster than the grid, and behind-the-meter gas plants are already powering AI campuses. Gas will likely remain a workhorse bridge fuel even as nuclear and renewables scale, with carbon and permitting considerations shaping its role.

Edge AI

As inference grows and latency-sensitive AI moves into applications, edge AI — distributed compute close to users — will expand alongside the giant remote training campuses. Expect a two-tier geography: massive, power-rich training factories in rural and post-industrial areas, and a proliferating layer of smaller inference and edge sites near population centers.

Autonomous systems

Autonomous vehicles, drones, and robotics will drive demand on both ends — centralized training and simulation, and distributed low-latency inference. The compute backbone behind physical automation will be a growing, durable source of data center demand through 2035.

National security implications

Compute has become strategic. Expect continued attention to domestic capacity, supply-chain security for chips and equipment, the resilience and security of the grid serving compute, and the treatment of data centers and powered land as matters of national interest. This elevates the strategic value of US powered land and the infrastructure that serves it.

The throughline to 2035: demand for compute keeps rising; the grid struggles to keep up; so power — firm, fast, and on-site where necessary — becomes ever more valuable. Every trend reinforces the same conclusion that runs through this guide: controlling powerable land and the infrastructure that energizes it is the central opportunity of the AI infrastructure era.

Bonus: Checklists & Site Selection Scorecard

Practical, printable diligence tools. Use them as a starting framework — every site, utility, and jurisdiction differs, so adapt and verify with qualified professionals.

Data Center Land Checklist (50 points)

A broad screen for evaluating a prospective data center parcel across power, site, connectivity, water, regulatory, and economic factors.

  1. Serving electric utility identified
  2. Available power capacity confirmed with utility
  3. Distance to nearest high-voltage transmission
  4. Voltage and spare capacity of nearby lines
  5. Proximity to a substation with capacity
  6. Interconnection queue position/timeline understood
  7. Estimated cost to deliver target MW
  8. Behind-the-meter generation feasibility
  9. Natural gas pipeline access (for on-site gen)
  10. Target deliverable MW vs. project need
  11. Total acreage adequate for program
  12. Land is contiguous and unbroken
  13. Room for future phases/expansion
  14. Topography flat to gently sloping
  15. Geotechnical/soils suitability
  16. Outside FEMA floodway/high-risk flood zone
  17. Stormwater management feasible
  18. Seismic and natural-disaster risk acceptable
  19. Phase I environmental complete
  20. Phase II environmental (if warranted)
  21. Wetlands/waters delineation
  22. Endangered-species/habitat review
  23. Historical/archaeological review
  24. Contamination/remediation scope (if any)
  25. Long-haul fiber proximity
  26. Multiple carriers available
  27. Dark fiber availability
  28. Physically diverse fiber paths possible
  29. Latency profile fits intended workload
  30. Municipal/well/surface water access
  31. Water rights and volume confirmed
  32. Reclaimed/non-potable water option
  33. Sewer capacity available
  34. Zoned industrial or data-center use
  35. Rezoning/variance needs identified
  36. Local jurisdiction supportive
  37. Setback and height requirements checked
  38. Noise/aesthetic ordinances reviewed
  39. State/local tax incentives available
  40. Sales-tax exemption on equipment
  41. Property-tax abatement potential
  42. Road access and weight limits adequate
  43. Rail access (for heavy equipment)
  44. Construction labor availability
  45. Operations labor availability
  46. Proximity to demand/market fit
  47. Title clean / encumbrances reviewed
  48. Easements and ROWs identified
  49. Control structure (option/land bank) in place
  50. Exit/monetization path defined

Brownfield Redevelopment Checklist (30 points)

Specialized diligence for converting a retired industrial site — coal plant, mill, or factory — into a data center campus.

  1. Prior industrial use documented
  2. Existing electrical service capacity
  3. On-site substation present and condition
  4. Switchyard present and condition
  5. Existing transmission ties and voltage
  6. Interconnection rights transferable/intact
  7. Utility willingness to re-serve the load
  8. Usable capacity of existing infrastructure verified
  9. Demolition scope and cost estimated
  10. Salvage value of existing structures
  11. Phase I environmental complete
  12. Phase II sampling completed
  13. Contamination extent characterized
  14. Remediation plan and cost
  15. Regulatory remediation status/program
  16. Liability protections (e.g., applicable programs)
  17. Asbestos/lead/hazardous materials survey
  18. Existing water intake/rights
  19. Cooling-water feasibility
  20. Rail spur condition and access
  21. Existing zoning (industrial) confirmed
  22. Large contiguous acreage confirmed
  23. Soil/foundation suitability (heavy industrial)
  24. Existing roads and site access
  25. Gas service availability
  26. Fiber proximity to the site
  27. Community/political support
  28. Incentives for redevelopment available
  29. Timeline advantage vs. greenfield quantified
  30. Powered-value vs. industrial-value gap modeled

Utility Due Diligence Checklist (50 points)

A deep dive on the single most important factor — power — and the utility relationship behind it.

  1. Serving utility and service territory confirmed
  2. Regulated vs. deregulated market
  3. Grid operator / RTO / ISO (or TVA, etc.)
  4. Current available capacity for new load
  5. Planned capacity additions
  6. Generation mix serving the area
  7. System reliability history
  8. Nearest transmission line voltage
  9. Spare capacity on nearby lines
  10. Distance to interconnection point
  11. Substation proximity and capacity
  12. New substation feasibility and cost
  13. Interconnection process and steps
  14. Interconnection queue position
  15. Study timeline (feasibility/system impact)
  16. Estimated network upgrade costs
  17. Cost allocation (who pays upgrades)
  18. Large-load tariff terms
  19. Energy rate ($/kWh) and structure
  20. Demand charges
  21. Rate escalation history/risk
  22. Minimum take/contract terms
  23. Power factor/quality requirements
  24. Redundant feeds available
  25. Dual-substation feasibility
  26. Behind-the-meter generation allowed
  27. Standby/backup tariff terms
  28. On-site gas turbine feasibility
  29. Gas pipeline capacity and pressure
  30. Renewable/PPA options
  31. Nuclear/SMR co-location potential
  32. Curtailment/interruptible options
  33. Utility's data center track record
  34. Utility staffing/responsiveness
  35. Letter of intent / capacity reservation
  36. Conditional power commitment terms
  37. Milestone and deposit requirements
  38. Transformer/switchgear lead times
  39. Construction coordination with utility
  40. Metering and SCADA requirements
  41. Easements for utility infrastructure
  42. Future capacity expansion path
  43. Water utility capacity (for cooling)
  44. Water rate and availability
  45. Sewer capacity
  46. Stormwater/discharge permits
  47. Environmental/air permits for generators
  48. Regulatory approvals for new load
  49. Stakeholder/community considerations
  50. Contingency if power is delayed/denied

Data Center Site Selection Scorecard

A weighted worksheet to compare sites objectively. Score each factor 1–10, multiply by the weight, and sum. Power-related factors carry the most weight by design — reflecting that power is the binding constraint.

FactorWeightScore (1–10)Weighted
Power availability & timeline25%______
Power cost & utility terms15%______
Transmission/substation proximity10%______
Acreage, contiguity & topography8%______
Zoning & entitlement certainty8%______
Fiber connectivity & diversity8%______
Water availability for cooling7%______
Environmental/flood condition6%______
Tax incentives5%______
Labor & construction access4%______
Market fit & exit4%______
Total100%___

Tip: any score of 1–2 on "power availability & timeline" is usually a kill criterion regardless of total — a site you cannot power is not a data center site.

Work With Carson

Have a Question? Talk to Carson

Whether you're buying, selling, or evaluating a commercial real estate deal, Carson Jones and Passive Investments can help. Text to start a conversation, or explore his brokerage services.

Glossary & Keyword Index

Quick definitions of the core terms in this guide, useful for orientation and for search.

Megawatt (MW)

One million watts of power; the unit data center capacity is measured and leased in.

Gigawatt (GW)

1,000 MW; city-scale power, the frontier of AI mega-campuses.

Critical IT load

Power available to computing equipment, separate from cooling/overhead.

Powered land

Land with secured access to large electrical capacity — the prized input.

Powered shell

A building with power and cooling in place; tenant completes the interior.

Shovel-ready

Entitlements, zoning, and utilities in place so construction can start.

Interconnection

The physical/contractual connection of a facility to the grid.

Interconnection queue

The backlog of projects awaiting grid-connection studies and approvals.

Substation

Infrastructure that transforms voltage and connects a site to the grid.

Switchyard

High-voltage area where transmission lines connect and are switched.

Behind-the-meter

On-site generation on the customer's side of the utility meter.

Hyperscale

Very large facilities for major cloud/AI operators.

Colocation

Leasing space and power in a provider's facility (retail or wholesale).

Edge computing

Distributed compute near users to cut latency.

Brownfield

Previously developed industrial site, often with existing power/zoning.

N+1 / 2N

Redundancy levels: one spare (N+1) vs. full duplication (2N).

PUE / WUE

Power and Water Usage Effectiveness — key efficiency metrics.

Cost per MW

All-in cost to build a megawatt of critical IT capacity.

Yield on cost

Stabilized NOI ÷ total development cost.

Development spread

Gap between yield on cost and exit cap rate — the development profit.

AI factory

Industrial-scale facility built to train and serve AI models.

GPU cluster

Thousands of accelerators networked to train/serve AI.

SMR

Small modular reactor — compact nuclear for firm on-site power.

TVA

Tennessee Valley Authority — federal utility across the region.

Keyword index: data center land, powered land, data center development, data center investment guide, data center site selection, how much power does a data center need, data center land requirements, brownfield redevelopment data center, coal plant conversion data center, TVA data center sites, hyperscale development, AI infrastructure real estate, data center opportunity zone, data center due diligence, data center power availability, megawatts, gigawatt, interconnection queue, substation, switchyard, behind-the-meter generation, N+1 redundancy, 2N redundancy, colocation, edge computing, powered shell, water usage, dark fiber, cost per MW, yield on cost, development spread, AI factory, GPU cluster, small modular reactor, Ashburn, Dallas, Phoenix, Atlanta, Nashville, Memphis.

eXp Commercial · Passive Investments

Need brokerage services?

Carson Jones is a licensed commercial real estate advisor and business broker with eXp Commercial. For powered-land and data center site evaluations, property acquisitions and dispositions, business sales, and investment advisory — visit Passive Investments.

Visit Passive Investments →
Educational only — not legal, tax, engineering, or investment advice. Data center development sits at the intersection of utility regulation, securities, environmental law, and heavy construction, and every fact here — power rates, queue timelines, incentives, cooling figures — varies by utility, state, and project. Megawatt math, cost ranges, and market data are summarized for orientation, not reliance. Before committing capital or signing an option, engage qualified utility/power consultants, environmental counsel, a site-selection engineer, and a tax advisor. Figures reflect general 2025–2026 industry ranges and will change.